home TRC Home Page           previous Table 3.2

ILC-TRC logo Table 4.1
Progress from LC Test Facilities
(December 1995)


Click here to update your test facility information for Table 4.1.


Facility Constr.
Start
Constr.
Complete
Tested or to be
Tested During
Construction
Accomplished or to be
Accomplished During
Operation
Still to be
Done
Other Things
to do/
Limitations

SLAC

FFTB 1989 1993 Alignment
Stabilization
(mechanical and thermal)
Spot monitors
BPM's
Injected beam with

Spot demagnified by 320 to 70 nm

Chromatic properties verified
Instrumentation and tuning
Beam-based alignment developed
E144 nonlinear QED observed
Finish systematic alignment and beam studies
Nanometer RF-BPM's

ASTA/Test Lab 1992 on-going 50MW klystrons
SLED II
1.8 m detuned structure tested to 67 MV/m
SLED II tested to 205 MW output
50 MW PPM focused klystron
SLED II tested to higher power
75 MW klystron to be developed

ASSET at SLC 1994 1997 1.8 m detuned structure wakefields verified 1.8 m damped/detuned structure wakefields to be measured

NLCTA 1993 1997 Overall assembly of rf system Not yet started Injector commissioning
Beam loading compensation
Beam breakup tests
Transverse rf field tests
Two-klystron modulator tests
Injector upgrade
Blumlein modulator
Construction of instruments

KEK

ATF
1.54 GeV Linac & DR
1992 1996 Multibunch generation
(20, 2 x , 2.8 ns spacing)
33 MV/m with S-band
Dual-iris SLED-I
S-band choke mode structure
Bunch-to-bunch instrumentation
Polarized electron gun
Linac loading compensation by -frequency
Beam-based tuning in linac and DR
Damping by wigglers
Double kicker extraction
Waveguide-damped rf cavity
Multibunch beam dynamics (no. of bunches no. of trains = 10 5 to 60 2)
One-stage compressor
Positron source test
Final focus test
Polarized rf gun
Polarized positron source
X-band technologies
90-bunch trains
1.4 ns spacing
Full energy positron production

BINP

VLEPP
400 MeV
1992 1997 60 MW klystron
1 MV DC voltage system
VPM (rf pulse comprsn.)
1 m structures
5 m submodule of VLEPP
High power test of structure
High power test of VPM
Alignment
Super-precise BPM's
Micromovers
120 MW gridded-gun klystrons with PPM focusing
Feedback system
X-band technology
Single bunch dynamics
Cost estimates

CERN-CLIC

CTF1 1989 1995 RF gun photocathode
Laser system
Short bunch measurement, 30 GHz accel. structures
Demonstration of two-beam principle
Generation of 35 nC/b, 76 MW 30 GHz power
No 30 GHZ breakdown up to E = 125 MeV/m,
(E) = 94 MeV/m in CLIC acc. section
Testing 33 GHz BPM & 30 GHz transfer section
Beam loading compensation
Bunch compression with trains, obtain 30 nC with = 2 ps

CTF2 1996 1999 New 2.5 cell RF gun
3 GHz accelerating sections adapted to high charges
Not yet started Beam loading compensation with trains
Bunch compression
1 C (48 bunches)
30 GHz reaccel. to 320 MeV
Active alignment system
Wakefield studies

CESTA 1993 1997 Generation of bunched beam (1 cm spacing)

DESY

SBLC
Test Facility
400 MeV
1992 1996 Modulator I tested
150 MW klystrons I & II tested
6m sections with HOM
ROBAX-ceramic support
Injector design
BPM's
Appropriate bunched beam generated with compression to 250 ps
Quadrupole vibration feedback successful, with 12 dB attenuation between 1-20 Hz
Beam dynamics of single and multibunch
(125) trains with 8, 16, 24 ns spacing (300mA)
Machine too short to study complete effects, filamentation, etc.
Need RF pulse shaping to correct beam loading

TESLA
Test Facility 500 MeV
1993 1997
Processing steps
Fabrication methods
Lorentz force control
Cryogenics, RF power
Injector design
Not yet started RF/Energy control
Cryo heat leak, static, fundamental, HOM
Alignment stability
Vibration, microphonics
High-charge injection
Long transv. wakes, single bunch, multibunch
Cavity misalignment
Cryo procedures warm up / cool down
In-situ HPP
Dark current, beam losses and radiation
Refine cost estimates of alternate designs for cavity fabrication
High-efficiency klystron
SMES Modulator
TESLA design
Overall cost estimates

LBNL

RTA 1995 2002 Not yet started Cost and efficiency issues in drive-beam generation
Beam transport and BBU limits
RF production and stability
Performance and efficiency of an extended system

Facility Constr.
Start
Constr.
Complete
Tested or to be
Tested During
Construction
Accomplished or to be
Accomplished During
Operation
Still to be
Done
Other Things
to do/
Limitations




Click here to update your test facility information for Table 4.1.
This Table is available in both PDF and PostScript format:
Download table4_1.pdf
Download table4_1.ps
PDF, PostScript, and WWW browser information

home TRC Home Page           previous Table 1.2

Best viewed using Netscape 3.0 with Times 12 font.

For information about this document,
contact E. Mitchell, elm@slac.stanford.edu

This page modifed: March 31, 1997 - 1 p.m. PST - elm