R. Keitel, D.Bishop, D.Dale, H.Hui, S.Kadantsev, M.Leross, R.Nussbaumer, J.Richards, E.Tikhomolov, G.Waters (TRIUMF)
Implementation and commissioning of the EPICS based control system for the ISAC radioactive beam facility was completed. The target ion source, mass separator, and low-energy beam-lines [1] started beam production for experiments. In parallel, controls for the accelerator system, a radio-frequency quadrupole followed by a drift-tube linac, and several high-energy beam-lines were implemented and commissioned. The number of controlled devices more than doubled since the last report. An overview of relational database usage, software engineering and quality control methods used will be given.
[1] R. Keitel, et al., 'Design and Commissioning of the ISAC Control System at TRIUMF', ICALEPCS99