Minutes from the 08/09/05 LCLS SLC IOC meetings (updated for Aug 26 progress): (1) Updated Task Lists: Done Tasks since 8/02/05 Who When ------------------------------------------ --------------- ---------- * Large database bug fix Debbie Aug 12 * Message reply utility Diane Aug 12 * BSAC prep message and collection area Debbie Aug 24 * BSAC EPICS subroutines and msg passing Debbie, Diane Aug 24 * BSAC test EDM displays and simulator Steph Aug 12 * BSAC async function added Steph Aug 12 * Get rid of slcExec and cstrHdlr kluges Steph Aug 12 * XL01 to XL05 BSAC calibration D,D,S,MikeZ Aug 26 * Add cdvw4 RTEMS IOC for testing (XL04) Steph Aug 26 * Add micro offline step to dbgen checkout Nancy Aug 12 Major Tasks Who When ------------------------------------------ --------------- ---------- * BSAC code/test finished Debbie, Diane Sep 06 * Magnet SLC design review Kristi Aug 31 * Magnet EPICS design review Kristi Aug 31 * Magnet code/test finished Kristi Sept * Change iocLogServer for CMLOG Steph Sept * Decide on SLC PNET timing diags support Steph Sept * ICD - EVR (w/Dayle) D, D, Kristi Sept * ICD - BPM (w/Till) Debbie, Diane Sept * ICD - Toroid and GADCs (w/Doug) Debbie, Diane Sept * ICD - Fast Feedback (w/Steph) D, D, Kristi Sept * ESD - IOC naming and restrictions Steph Sept * LCLS SLC modelling database setup, etc Mark Woodley Next year Loose End Tasks Who When ------------------------------------------ -------------- ----------- * Update VDCT/database standards Steph Aug 31 * Thread priorities Steph Sept * slcExec to Check CSTR CDSC bit for FECC Diane Sept * slcCmlog change to honor stop flag Steph Sept * Add how-to-add-an-slc-aware-ioc Steph Sept * Timing of 10 sec update not right Steph Sept * CSTR/ASYNC code review Steph Sept * Wrong IPL time when not booted from SCP Steph Sept * slcCmlog error metering Steph Sept * Pulse ID in SCP correlation plots MikeZ Oct? * Update specs All As needed * Update record naming conventions All As needed TBD: * Increase max number of micros * Second production proxy? * Production "domain" split * MCC CA server change for controlling CAMAC power supplies (need estimate) (2) Vacation: Kristi - Sept or later Steph - Sept 26 to 30 Tony - gone until Oct (3) BSAC: BSAC Device Control States From MikeZ: * offline = no hardware or cabling * maintenance = not used in high level applications, HW/SW testing * checkout = used in high level apps, HW/SW tests OK, OPS testing * online = ready to use, OKed by OPS Bob Dalesio says no SCP wire-scanner support. (4) Magnet: Kristi will have a design review soon. She is adding a stringout record per magnet device for status. Kicker uses LGPS and SMPS and gated ADC for pulse amplitude.