Next Linear Collider Test Accelerator Controls

 

Wiener VME Crate PS Failure

The Wiener VME Crate PS used for TR01 burned up on the monring of Tuesday, August 28, 2001. Later that same day the failed power supply was Fed-Xed to the US distributor in the mid-west.  The following morning, a loaner power supply that Bob Fuller located at Babar (compliments of Perry Anthony) was installed into TR01, and the crate was brought back online.  Since the cause of the power supply failure is unknown  the crate was brought back up without any modules and then slowly modules were added one-by-one.  In Table1 below, moving from left to right, the first column lists the order that modules were replaced into the crate and the crate statisticts are noted in the subsequent rows.


 
 
Table 1
Description Empty mvme761 vmic2534
cable
mvme2700 vmic2435 vmic4100 lecroy1176 caenV265 
#2
caenV265
#1
caenV265
#0
Remove 
caenV265
#1
Remove
caenV265
#0
Status  OK OK OK OK OK OK OK OK OK OK OK OK
+5V (A) 2 2 2 7 8 10/11 13 16 16 19 16 16
+12V (A) 0.1 0.1 0.1 0.1 0.1 0.2 0.2 0.4 0.6 0.8 0.6 0.4
-12V (A) 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.2 0.3 0.3 0.2
Power (W) 15 15 15 35 45 55 70 80 90 110 90 85
Can Addr 1 1 1 1 1 1 1 1 1 1 1 1
General Call 127 127 127 127 127 127 127 127 127 127 127 127
Speed  (Mbaud) 1 1 1 1 1 1 1 1 1 1 1 1
Fans Speed (Rpm) 2400 2400 2400 2400 2400 2400 2400 2400 2400 2400 2400 2400
Fan Temperature (deg) 82 82 82 82 84 84 86 86 86 96 87 87
Bin Temperature (deg) 89 89 89 89 87 91 95 95 95 95 98 98
Fan Time (hrs) 6476 6476 6476 6476 6476 6476 6476 6476 6476 6476 6476 6476
PS Time (hrs). 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3 4.3