Status

8 June 2004

Note compiler: J. Nelson

Contributors: R Chestnut, R Hall, J Rock, D Rogind

 

SLED FDBK through SCP slow feedback

     (still true) Folks keep turning it off.  Not clear if it’s the labview or the fdbk.  BM works just fine though   Janice will make time to troubleshoot, perhaps not until after ITRP visit.

 

paoutdata mat files compatible with matlab 7?

     No news just yet. Matlab 7 coming end of summer. 

    

SIS waveforms archived every hour (plus on change)

     done

         

MacNair module support of aes

Debbie has it working in the test closet.  Next step is to test signals or boot into TR06.

 

RMS/BIG requirements for 8-packs structures: Ron gets to choose which is easier – one loop for all MacNairs in tr09 and tr06, or one loop for each ioc

 

(Ron will look or send to Janice) Will need to be able to archive the gain and set the gain (internal to module). (potentially different for each module)

 

2-pack PLC coming in October-ish. 

(still true) ~20 signals as yet undefined.  Janice will ask for TP printouts for this PLC too…

 

Plans for the future

(This is still true.)  One or two 2-packs, plus the work in these minutes.  Is ˝ recent output a good estimate for the rest of the fiscal year?  Ron will talk with Schultz and get back if this isn’t a good estimate.

 

NLCTA/8-pack summary display

Trip rate for past 24 hrs.  Ron’s gonna think about it.

 

Reboot trips

NCLTA folks are building a circuit for the deadman and for the voltage inverter now.  Anticipated installation 6/18.

 

Ron has a plan for something else to try.  Probably ready for test in a few weeks – kinda goes with:

About the change from subr records to sequence program processing takes a few weeks to get the code ready and a week to test, when not RF processing.

 

AFG driver code is done

(no new status)  Still waiting for Frisch to deliver an AFG.