Meeting
Agenda
2 March
2004
In
attendance: J. Nelson (notetaker), R.
Chestnut, R. Hall, J. Rock, S. Smith
Slow
archiver?
Bob reports: factor of 2
faster! Yeah! One more thing to try, otherwise…
SLED FDBK
through SCP slow feedback
Ed did a wonderful job creating this, but
unfortunately we haven’t had a chance to test it yet (hardware
problems/tests). Soon?
SIS
waveforms archived every hour (plus on change)
We do want this and around early April.
List of
phase 2a signals
Steve made a
nice list. Judy can now crank out the
databases. Thanks, Steve!
Right now,
the only ADC channels being used are 0 & 1 (twt5:inp:fwd and
twt6:inp:fwd). If these need to be
lobotomized, please let Janice know and she/Joe can move wires around.
Prep for
phase 2a
Judy thinks DTZ3 is ready to go in the database. Last today/tomorrow we can test with triggers
and signals. The WFs also need archiving
(like DTZ0-2) – will add to list after testing. Thank you, Judy.
macnair
module support of aes
Not yet. Ron is working on this. Database coming soonish.
Will need to
be able to archive and set the gain.
Will need to
have AES on structures in tunnel April 1stish
PLC checkout
(eventually) Janice is beating on the list in her
free time.
Newplc
(no new information) Rumored to be coming in a few
weeks… Nice email from Alan Hill. Janice
has instructions for what to try when installed and ready to go.
Realm split
(ditto)
This is ongoing. Ops should expect just
a few small interruptions in the future.
TR06 is coming…
Up there on the roof. Now has 20 MacNair modules in the crate, but
not a processor… Hmm. We’ll see.
ELOG
No
new news. Next, Bob, Keith, and Spence
will discuss wants and work needed.
2-pack PLC coming in April-ish.
~20 signals as yet undefined.
New Vacuum coming with phase II-a
(still true) Judy made leaping, bounding progress and
is now waiting for Cassel to assign PLC channels (in March probably).
SIS missing pulses
(still true) This is obviously hardware. Joe and Janice are working on it. Maybe fixed???