Wednesday,
Nov. 20th, 09:00 am, POM/FLORA Room in B280
a)
Choose the highest level assembly drawing for which there is a complete
drawing package for an existing device that we plan to build more of for
the LCLS.
b)
Identify the corresponding WBS Number.
c)
Using Inj_dwg.xls, fill in Drawing Name as shown on the drawing, and Drawing
Number.
d)
Using whatever information is "readily" available, fill in Number of Sub-Drawings
and makean estimate of Percentage
of Sub-Drawings Ready for LCLS Bid/Construction/Assembly.
e)
If the subject assembly drawing is available electronically, indicate the
Drawing Filename and the File Source.
2.Review
of the "required lead times" in the latest version of the long
lead items list(021106LongLeadItems.xls). Please bring to the meeting your
corrections and justifications.
3.Laser
system PED review. Scope (laser design, laser room layout, etc.);
role of Laser Advisory Committee (LAC), input from Laser Workshop, etc. Bolton
_______________________________________
Future
meetings:
Nov.
27. No meeting.
Dec.
4. 1) Electrooptic device plans. Dowell
2)
Final decision on drawings-documentation
format.
Dec.
11. 1) RF FF. Akre/Schmerge
2)
RF source. Akre
________________________________________
*Relevant
files at winsan1/groups/Ad/Drop Boxes/Clendenin .
S20 Injector home page at http://www.slac.stanford.edu/grp/ad/S20Injector/ .