Injector Goals for CD-2A (April 2003)
Dec 02 System for documenting drawings established.
Feb 03 Full count of existing drawings.
Mar 03 Estimate of number of drawings yet to produce.
Feb 03 RF gun thermal/stress analysis.
Mar 03 RF gun specifications and preliminary design.
Dec 02 Preliminary beamline layout.
Jan 03 Final choices for oscillator and amplifier
system for (done in concert with LAC and includes costing).
Jan 03 Bare bones spares/replacement strategies
(includes costing & further details to come from actual prototypical work).
Mar 03 Laser oscillator bid package
Jan 03 VME
IOC or multibus CAMAC or hybrid?
Jan 03 EPICS integration plan.
Jan 03 BITBUS or DAC/SAMs?