06 November 2002

 

Injector Goals for CD-2A (April 2003)

 

General

 

Dec 02 System for documenting drawings established.

 

Feb 03 Full count of existing drawings.

 

Mar 03 Estimate of number of drawings yet to produce.

 

Gun/Load-Lock Systems

 

Feb 03 RF gun thermal/stress analysis.

 

Mar 03 RF gun specifications and preliminary design.

 

Electron Beamline

 

Dec 02 Preliminary beamline layout.

 

Laser Systems

 

Jan 03 Final choices for oscillator and amplifier system for (done in concert with LAC and includes costing).

 

Jan 03 Bare bones spares/replacement strategies (includes costing & further details to come from actual prototypical work).

 

Mar 03 Laser oscillator bid package

 

ESD Systems

 

Jan 03            VME IOC or multibus CAMAC or hybrid?

 

Jan 03 EPICS integration plan.

 

Jan 03 BITBUS or DAC/SAMs?