The LCLS Project preliminary schedule shows construction beginning in FY06. However, the plan is to build the injector in FY05 as a long-lead procurement project. Thus the Project Engineering Design (PED) for the injector will take place principally in FY03 and FY04. The PED includes some prototyping.
The funding schedule for the LCLS will provide only very modest funds for the injector PED in FY03. The plan is to provide the bulk of the injector PED funding in FY04. Some PED work will continue in FY05 during construction.
NEW (11/13/02): First
FROG (IR) trace at GTF observed.
FY03 Prototyping:
GTF
Laser
E-O
RF
FF
RF Source
BPM Modules
Workshop on Laser
Issues for Electron RF Photoinjectors (LI-ERP), SLAC, October 23-25,
2002.