    User name Vinod

    Log entry time 14:29:39 on October 9,2004

    Entry number 23

    keyword=day shift summary

    1. access into FFTB to look at undulator equipment (JCS, AM & KM)
    2. beam tuning (Iverson)
    clean beam to the dump, PLIC signal less than 2 (no beam loss)
    moved phase ramp -5 degree, steered the beam up a few mm on the last three BPMs in the FFTB.


    FIGURE 1

    FIGURE 2