June/03 Commissioning Interface/Infrastructure Updated June/11/03 ============================================== TSFi Apr May June ---- 14 21 28 5 12 19 26 2 9 16 MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSM 1) Layout mod ***************************D D Jeff (Finisar footprint, LVDS chan-link spacing/Pwr bootstrap, mechanical issues) 2) Load proto2/3 ****************D Jeff (Load another full TSFi and 3rd with only the neighbor data part) 3) TSFi part order S************************D* Jeff (need to check pre-ordered long lead item's arrival too) 4) LVDS cable/connector order S*******************D**** Jeff (we need 20 cables to start with) 5) TSF->ZPD test ***********************1*****D Xuedong (Different patterns, all ZPD channels - Need TSF output play Try TSF+ZPD in 1 crate first, then separate crate driven by master crate) 6) Probe signals **************D Jeff, Xuedong, Su Dong (Detailed signal quality checks on scope). 6a) GLINK Synch test ********D Su Dong 7) Slow Mon setup/test *************D Nicolas Berger 8) TSFi cables ****D **************D Lupe, Su Dong (TSFi neighbor cables, TSFi->BLTi cables) 9) BLT Mem Map ***********D Su Dong 10) TSF->BLT test ******************D Xuedong, Marc, Su Dong 11) DCH->TSF test ***************************D Jamie, Gerald, Marc (with 3 chip TSF) 12) TSF neighbor test *******D Marc, Scott (3 chip TSF firmware loopback) 13) TSF/TSFi signal check ********D Scott (Scott would like some detailed scope probing to be sure) 14) TSFi PCB fab. (8 preprod) ****S********D Jeff (5 day delivery available) 15) TSFi assembly (8 preprod) *******D***** Jeff (5 day delivery available) 16) PreProd TSFi testing for first 8. ********* Xuedong, Su Dong 17) TSFi front panel ***************************** Howard, Su Dong ZPDi Apr May June ---- 14 21 28 5 12 19 26 2 9 16 MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSM 1) Layout mod ************************************D Jeff (still to decide add LVDS connector mounting rings or not, mechanical) 2) ZPDi part orders S************ Jeff (may want do earlier for anything takes longer than 2 weeks) 3) ZPD->GLT test *****************D Xuedong (need GLTi firmware mod. first) 4) TSF->ZPD test ***********************D Xuedong (same as TSFi test 5) 5) ZPDi PCB / assembly S*************** Jeff 6) ZPDi testing Xuedong (for first two) 7) ZPDi front-panel ******** Howard, Su Dong Infrastructure Apr May June -------------- 14 21 28 5 12 19 26 2 9 16 MTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSM 1) Fiber spec ********D Mark, Su Dong 2a)Fiber splitter fab ***S********************1********************D Mark/Lupe 2b)Fiber splitter mount **********************************************D Ray, Gibson 3) Fiber lab. testing D Ray 4) Fiber installation/test *****D*** Ray, Valerie, Nicolas (May26-29 12hr MD each day) 5) New DCT rack power *************************************D Ray 6) New DCT DAQ crate *****************D*** Chris O'Grady 7) TSF Slowmon cables **D Ray 8) TSF Slowmon ************************D Nicolas (Slow mon for TSF new and old at IR2) 9) Test crate *************A********************************************D Valerie (Additional test crate to support Lab. need)