L1 Upgrade Software todo list
Tentative Schedule Overview
By Sept 1st
Milestone: Online Release
- Define Online Config objects
- Define Offline (sim) Config objects
- Global framework structure (including testing framework)
- BLT Sim Modules
- Deploy Digis (including TC handling)
- Install initial online config -> DB
By Oct 1st
Milestone: First complete L1Sim build
- ZPD Sim Modules
- GLT Modules
- PTD Sim Modules
By Nov 1st
Milestone: First L1Sim release candidate (RC)
- Validate simulation code
- Online Validation tools
- Install remaining online config -> DB
By Dec 1st
Milestone: Final L1Sim RC
- Install offline config -> DB
- Refine online validation tools
- Finalize hardware-sim validation
By Jan 1st
Milestone: System deployment
- Deploy final L1Sim code
- Documentation
General Simulation
| Item |
Priority |
Due |
Primary |
| Global Switch Framework |
Med |
Sept 1 |
ET |
| Global Switch Config |
Med |
Sept 1 |
ET |
| Simple L1SimApp |
High |
Sept 1 |
ET |
| timebuffer file input in framework |
High |
Sept 1 |
ET |
| sim latency object |
Med |
Sept 1 |
OI |
|
|
|
|
|
|
|
|
|
|
|
|
DCT Simulation
| Item |
Priority |
Due |
Primary |
| TSF Updates |
Med |
Sept 1 |
JB |
| ZPD Finder Module |
Med |
Oct 1 |
OI |
| ZPD Fitter Module |
Med |
Oct 1 |
OI |
| ZPD Decision Module |
Med |
Oct 1 |
OI |
| BLT Module |
Med |
Oct 1 |
AWB |
| PTD Module |
Med |
Oct 1 |
AWB |
| Create L1DZpdConfig |
Med |
Sept 1 |
MM |
|
|
|
|
GLT Simulation
| Item |
Priority |
Due |
Primary |
| Delay, Match, Combine Module |
Med |
Oct 1 |
VH |
| Object Count Module |
Med |
Oct 1 |
VH |
| Decision Module |
Med |
Oct 1 |
VH |
| Select Trigger |
Med |
Oct 1 |
VH |
| Use online GLT config code |
Med |
Oct 1 |
VH |
| Update GLT digi? |
High |
Sept 1 |
VH |
|
|
|
|
|
|
|
|
Offline
| Item |
Priority |
Due |
Primary |
| Test L1DTsfDigiP |
High |
Sept 1 |
OI |
| Deploy L1DTsfDigi |
High |
Sept 1 |
OI |
| Write Zpd root digis |
Low |
Oct 1 |
OI |
| ZPD Digi->TC conversion |
Low |
Oct 1 |
|
| TSF TC->Digi->TC comparators |
Low |
Oct 1 |
JB |
|
|
|
|
|
|
|
|
|
|
|
|
Configuration
| Item |
Priority |
Due |
Primary |
| New TSF Lut calibration |
Low |
Dec 1 |
SD |
| TSF Lut to DB |
Low |
Dec 1 |
JB |
| Global trigger/GLT objects to TrigConfig |
Med |
Sept 1? |
RB |
| BLT mask to DB |
High |
Sept 1 |
AWB |
| BLT algorithm to DB |
Low |
Nov 1 |
AWB |
| ZPD LUTs to DB |
Low |
Dec 1 |
MM |
| 'Smart' proxy |
Med |
Nov 1 |
AS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Tools
| Item |
Priority |
Due |
Primary |
| L1TNtupleRooApp |
Low |
Nov 1 |
ET |
| L1SimCheck module |
High |
Nov 1 |
ET |
| TsfDigiComparator module |
High |
Nov 1 |
ET |
| Trigger Display |
Mid |
Nov 1 |
NB |
| L1TFmon updates |
Mid |
Dec 1 |
IK |
| L1TOprMon updates |
Mid |
Dec 1 |
IK |
| Teststand convertor development |
|
|
ET |
|
|
|
|
Glossary
- AS - Andy Salnikov
- AWB - Anders Borgland
- ET - Eric Torrence
- IK - Itaru
- JB - Jamie Boyd
- MM - Masahiro Mori
- NB - Nicolas Berger
- OI - Olya Igonkina
- RB - Rainer
- SD - SuDong
- VH - Valerie Halyo
Page author: Eric Torrence
Modified: Monday, July 28, 2003
|