EMT Schedule: 17/06/98 ============= ======== Activities in UK ================ Jun 29: Start fabrication of 15 TPB's (2 week fab). Finish assembly of second crate. Prototype TPB's arrive from SLAC. Start production test-stand setup (3 weeks). Jul 13: Fabrication complete. Start assembly of two "preproduction" TPB's (1 week ass). Jul 20: Assembly complete. Start preproduction tests on two TPB's (1 week/TPB). Aug 3: Tests complete; start assembly of 13 production TPB's (2 week ass). Ship the two preproduction TPB's to SLAC (1 week). Aug 17: Assembly complete. Start acceptance tests on 13 TPB's, excluding UPC tests (2 days/TPB). Sep 21: Tests complete. Ship to SLAC (1 week). Activities at SLAC ================== Jun 18: FDR at SLAC. Jun 22: Ship prototype system back to the UK (1 week). Aug 10: Preproduction TPB's arrive at SLAC. Finish installing new backplane in original crate. Start preproduction UPC tests (2 weeks/TPB). Sep 7: Install crate at IR-2. Start UPC cable installation and checking (3 weeks). Start GLT integration (3 weeks). Sep 28: Production TPB's arrive at SLAC. Start acceptance tests with UPC and GLT (1 day/TPB). Oct 12: UPC and GLT tests complete. Start remaining full-system installation and commissioning (2 weeks). Oct 26: Installation and commissioning complete.