SLAC PEP-II
BABAR
SLAC<->RAL
Babar logo
HEPIC E,S & H Databases PDG HEP preprints
Organization Detector Computing Physics Documentation
Personnel Glossary Sitemap Search Hypernews
Unwrap page!
Det. Search
Who's who?
Meetings
FAQ
Images
Archive
Systems
Performance
Intern. region
Vertex Tracker
Drift chamber
DIRC
Calorimeter
IFR
LST
Magnet
Electronics
Trigger
Operations
Run Coordination
Contact Experts
Shift Takers Info
Operations Manual
Electronic Logbook
Ops Hypernews
Shift Signup
Check this page for HTML 4.01 Transitional compliance with the
W3C Validator
(More checks...)

Brown Out Procedure 

The procedure to be followed for the IFR, in case of a Brown Out, is:
  1. Switch IFR HV OFF(through the EPICS panel)
  2. Switch IFR LV OFF (in the Electronics House)
  3. Leave IFR Chillers ON
  4. Leave FEE crates ON
  5. Leave Monitoring system ON


Power outage 


Recovery procedure after power outage

    Last modified: 25 October 2003, 19:36:31