DIRC Operations Weekly Report

Period: Wednesday 2007/3/27 - Wednesday 2007/4/4

Oncall: Bradley Wogsland
Fast Monitoring: Alejandro Perez, Bradley Wogsland

File location: $BFROOT/www/Detector/DIRC/WeeklyReports/report_20070404.html
Plot directory: $BFROOT/www/Detector/DIRC/WeeklyReports/Plots/report_20070404

Contents


BaBar-PEP news

PEP peak lumi: ~8.3 x 1033 (previous week: ~9 x 1033)

BaBar integrated lumi:1.97 fb-1 (previous week: 3.41 fb-1)

Run 6 PEP delivery:2.07 fb-1 (previous week: 3.43 fb-1)

Run 6 total delivery: ~22 fb-1 Run 6 total BaBar recorded: 21.2 fb-1 including 0 fb-1 off-peak data

PEP activities this week:

  • None

    LCLS activities this week:

  • Broken water pipe shut down BaBar's cooling water 4/3

    Foreseen work opportunities (PEP down periods):

  • 8 hr MD planned for Wednesday

    BaBar activities/issues this week:

  • Came back up fairly well from the ROD

    DIRC activities

    See DIRC logbook for details

    Backgrounds

    Scheduled activities

    Pending Work

    Manpower situation

    Jose, Alejandro and Bradley rotating backup & on-call commissioning duties.