DIRC Operations Weekly Report

Period: Wednesday 2007/2/21 - Wednesday 2007/2/28

Oncall: Alejandro Perez
Fast Monitoring: Alejandro Perez, Bradley Wogsland

File location: $BFROOT/www/Detector/DIRC/WeeklyReports/report_20070301.html
Plot directory: $BFROOT/www/Detector/DIRC/WeeklyReports/Plots/report_20070221

Contents


BaBar-PEP news

PEP peak lumi: ~8.2 x 1033 (previous week: ~6.5 x 1033)

BaBar integrated lumi: ~3.2 (previous week: ~1.7 fb-1)

Run 6 PEP delivery:~3.3 (previous week: ~1.8 fb-1)

Run 6 total delivery: 9.9 fb-1 Run 6 total BaBar recorded: 9.6 fb-1 including 0 fb-1 off-peak data

PEP activities this week:

Foreseen work opportunities (PEP down periods):

BaBar activities/issues this week:

DIRC activities

See DIRC logbook for details

Backgrounds

Scheduled activities

Pending Work

Manpower situation

Bradley, Jose and Alejandro rotating backup & on-call commissioning duties

Links