DIRC Operations Weekly Report

Period: Wednesday 2007/1/17 - Wednesday 2007/1/24

Oncall: Jose Benitez
Fast Monitoring: Jose Benitez, Bradly Wogsland

File location: $BFROOT/www/Detector/DIRC/WeeklyReports/report_20070124.html
Plot directory: $BFROOT/www/Detector/DIRC/WeeklyReports/Plots/report_20070124 (empty)

Contents


BaBar-PEP news

PEP peak lumi: 0 x 1033 (previous week: NA)

BaBar integrated lumi: 0 fb-1 (previous week: NA)

Run 6 PEP delivery: 0 fb-1

Run 6 total delivery: 0 fb-1 Run 6 total BaBar recorded: 0 fb-1 including 0 fb-1 off-peak data

PEP activities this week:

  • Run 6 startup tuning. Beams soon.

    Foreseen work opportunities (PEP down periods):

  • Day shift 31.

    BaBar activities/issues this week:

  • DIRC HV half way (V1) while PEP is trying to inject.

    DIRC activities

    See DIRC logbook for details

    Backgrounds

    NA

    Scheduled activities

    Pending Work

    Manpower situation

    Currently Bradley and Jose rotating backup & on-call commissioning duties every 2 weeks. Alejandro trying to get a drivers license and car before becoming active.

    Links