Last modified: 28 October 2002
Highlights, Thumbnails,
Descriptions
Picture of rear
endplate near completion of drilling. Spot drilling for
grounding posts. Forward endplate machining and
inspection photographs here
and here. A picture
of the test drilling plate can be found here. Also, other
endplate machining pictures are here, here, here, and here
Pictures of beryllium section of the inner cylinder are here,
here, here, and here
Pictures of the first wire installed in the DCH at 4pm PDT on August 18 are here, here, and here.
Final wires installed on November 28 at 6pm PST, with photographs here,
here, here, here,
here, and here.
Back to top
Back to top
- Photo 1: Nando Ferroni and Jonathan Dorfan surveying wire
transport robots in TRIUMF clean room
- Photo 2: Stringer training with mockup at TRIUMF
- Photo 3: Richard Fernholz, Jonathan Dorfan, Robert Henderson
discussing stringing procedures in front of robots at TRIUMF
- Photo 4: Mauro Morganti and Andrea Gaddi in front of chamber
after test installation of outer cylinder
- Photo 5: Magnet coil for tension measurement
- Photo 6: Changguo Lu surveying tension measuring magnets
- Photo 7: Endplate test sector with installed feedthroughs and
extraction tooling
- Photo 8: Test insertion of chamber structure between transport
robots
- Photo 9: Richard Fernholz, Mauro Morandin, and Robert
Henderson surveying installed chamber structure
- Photo 10: Andrea Gaddi and Mauro Morganti test installing
second outer cylinder panel, with full tension load on endplates
- Photo 11: Chris Hearty and Mike Kelsey applying tension load
to endplates
- Photo 12: Software engineers Sandra Santi and Roberto with
Silvio Morganti testing robot operations
- Photo 13: Closeup of robot arm with magnetic gripper
- Photo 14: TRIUMF clean room with assembly fixture, installed
chamber structure, and wire transport robots
- Photo 15: Robert Henderson and Richard Fernholz making a test
hoist of mobile assembly fixture from top of fixed frame
- Photo 16: Closeup of Robert Henderson and Richard Fernholz
hoisting mobile assembly frame
- Photo 17: TRIUMF physicist crew on top of fixed assembly fram
- Photo 18: Richard Fernholz with side view of partially hoisted
mobile frame
- Photo 19: Mike Kelsey inserting central shaft into assembled
chamber endplates and inner cylinder
- Photo 20: Test hoist of chamber structure in mobile assembly
frame
- Photo 21: Closeup of spiders, tension rods, cables, and
measurement equipment for endplate deflection test
- Photo 22: Mike Kelsey taking deflection measurement on endplate
- Photo 23: Physicist and stringer crew after completion of
stringing at TRIUMF
- Photo 24: Day crew after completion of last shift on November
28
- Photo 25: Installation of final wire by evening crew on
November 28
- Photo 26: After completion of final wire insertion on November
28
- Photo 27: View of completed wire field
- Photo 26: Start of installation of final wire by evening crew
on November 28
Back to top
For comments, questions or changes to this page contact David MacFarlane
|