DCH QA Shift Schedule

DCH Data Quality Shift Schedule

[1999] [2000]
2001 [January] [February] [March] [April] [May] [June] [July] [August] [September] [October] [November] [December]

Last modified: 13 February 2001 by M. Kelsey

Shifts are scheduled for one week, beginning Wednesday day shift (8 am).

Please read the Shift Duties Web page.

Shifters are expected to coordinate the transition among themselves.


January 2001 -- No shifts scheduled or required
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31
February 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3
QA Voena  Voena  Voena
4 5 6 7 8 9 10
QA  Voena  Voena  Voena  Posocco  Posocco  Posocco  Posocco
11 12 13 14 15 16 17
QA  Posocco  Posocco  Posocco  Morganti  Morganti  Morganti  Morganti
18 19 20 21 22 23 24
QA  Morganti  Morganti  Morganti  Cavoto  Cavoto  Cavoto  Cavoto
25 26 27 28
QA  Cavoto  Cavoto  Cavoto  Posocco
March 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3
QA Posocco  Posocco  Posocco
4 5 6 7 8 9 10
QA  Posocco  Posocco  Posocco Tisserand  Tisserand  Tisserand  Tisserand
11 12 13 14 15 16 17
QA  Tisserand  Tisserand  Tisserand  Kelsey  Kelsey  Kelsey  Kelsey
18 19 20 21 22 23 24
QA  Kelsey  Kelsey  Kelsey  Del Re  Del Re  Del Re  Del Re
25 26 27 28 29 30 31
QA  Del Re  Del Re  Del Re  Posocco  Posocco  Posocco  Posocco
April 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3 4 5 6 7
QA  Posocco  Posocco  Posocco   V. Tisserand   V. Tisserand  V. Tisserand  V. Tisserand
8 9 10 11 12 13 14
QA  V. Tisserand  A. Weinstein   A. Weinstein Lei Zhang Lei Zhang Lei Zhang Lei Zhang 
15 16 17 18 19 20 21
QA  Lei Zhang Lei Zhang Lei Zhang K. Abe K. Abe  K. Abe  K. Abe
22 23 24 25 26 27 28
QA  K. Abe  K. Abe K. Abe  Paul Jackson Paul Jackson  Paul Jackson  Paul Jackson
29 30
QA  Paul Jackson  Paul Jackson
May 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3 4 5
QA Paul Jackson Lei Zhang  Lei Zhang Lei Zhang  Lei Zhang 
6 7 8 9 10 11 12
QA  Lei Zhang  Lei Zhang  Lei Zhang  Toki (not attended) Toki (not attended)  Toki (not attended)  Toki (not attended)
13 14 15 16 17 18 19
QA  Toki (not attended)  Toki (not attended)  Toki (not attended)  Posocco Posocco  Posocco  Posocco
20 21 22 23 24 25 26
QA  Posocco  Posocco  Posocco  A. Soha A. Soha  A. Soha  A. Soha
27 28 29 30 31
QA  A. Soha  A. Soha  A. Soha   V. Miftakhov V. Miftakhov
June 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2
QA V. Miftakhov  V. Miftakhov 
3 4 5 6 7 8 9
QA  V. Miftakhov  V. Miftakhov  V. Miftakhov  Ed. Hill Ed. Hill  Ed. Hill  Ed. Hill
10 11 12 13 14 15 16
QA  Ed. Hill Ed. Hill Ed. Hill  A. Onuchin  A. Onuchin A. Onuchin  A. Onuchin
17 18 19 20 21 22 23
QA  A. Onuchin  A. Onuchin  A. Onuchin  P. M. Patel P. M. Patel  P. M. Patel  P. M. Patel
24 25 26 27 28 29 30
QA  P. M. Patel  P. M. Patel P. M. Patel P. Robbe  P. Robbe  P. Robbe  P. Robbe 
July 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3 4 5 6 7
QA  B. Aubert  B. Aubert  B. Aubert 024  024  024  024
8 9 10 11 12 13 14
QA  024  024  024  025  025  025  025
15 16 17 18 19 20 21
QA  025  025  025  026  026  026  026
22 23 24 25 26 27 28
QA  026  026  026  027  027  027 027
29 30 31
QA  027  027  027
August 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3 4
QA 028  028  028  028
5 6 7 8 9 10 11
QA  028  028  028  029  029  029  029
12 13 14 15 16 17 18
QA  029  029  029  030  030  030  030
19 20 21 22 23 24 25
QA  030  030  030  Posocco  Posocco  Posocco  Posocco
26 27 28 29 30 31
QA  Posocco  Posocco  Posocco  032  032  032

Scheduled end of run. QA shifts below will over final OPR processing and any reprocessing done during shutdown.
September 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1
QA 032
2 3 4 5 6 7 8
QA  032  032  032  033  033  033  033
9 10 11 12 13 14 15
QA  033  033  033  034  034  034  034
16 17 18 19 20 21 22
QA  034  034  034  035  035  035  035
23 24 25 26 27 28 29
QA  035  035  035  036  036  036  036
30
QA  036
October 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3 4 5 6
QA 036  036  037  037  037  037
7 8 9 10 11 12 13
QA  037  037  037  038  038  038  038
14 15 16 17 18 19 20
QA  038  038  038  039  039  039  039
21 22 23 24 25 26 27
QA  039  039  039  040  040  040  040
28 29 30 31
QA  040  040  040  041
November 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1 2 3
QA 041  041  041
4 5 6 7 8 9 10
QA  041  041  041  042  042  042  042
11 12 13 14 15 16 17
QA  042  042  042  043  043  043  043
18 19 20 21 22 23 24
QA  043  043  043  044  044  044  044
25 26 27 28 29 30
QA  044  044  044  045  045  045
December 2001
Sun  Mon  Tue  Wed  Thu  Fri  Sat
1
QA 045
2 3 4 5 6 7 8
QA  045  045  045  046  046  046  046
9 10 11 12 13 14 15
QA  046  046  046  047  047  047  047
16 17 18 19 20 21 22
QA  047  047  047  048  048  048  048
23 24 25 26 27 28 29
QA  048  048  048  049  049  049  049
30 31
QA  049  049

Comments to Mauro Morandin <morandin@slac.stanford.edu>