| Test / Installation Phase |
Date |
Electronics Hardware Requirements |
Software Requirements |
| Complete Readout Chain Test on Prototype II |
3/1/98-3/15 |
- 2 FEAs
- 1 Data I/O Module (DIOM)
- 1 ROM/FCDM/FCPM/9u crate
|
- a-release Dataflow
- Dataflow-Proto II Hybrid DAQ
|
| HV Installation and Test on Drift Chamber |
4/24 - 4/27 |
- HV cables
- CAEN HV system and modules
- HV Filter box
- 6u crate + VME mP
- VME CAENET interface
- Workstation running EPICS
- Temporary Gas System Control, Monitoring and Safety Interlocks
|
- EPICS w/ CAENET interface driver
|
Electronics Install and Test,
Single Wedge |
4/28-5/31 |
- HV System + cables
- LV System + cables
- 3-6 FEAs w/cables
- 1 DIOM
- 1 Trigger IO mod. (TIOM)
- 1 ROM/FCDM/FCPM/9u crate
- Fiber-optic cables
- Forward endplate env. monitoring modules
- Slow Controls 6-u crate w/
-
- CANBUS interface
- CAENET interface
- SIAMs
- VSAM?
- cables
- Cosmic trigger counter
- Workstation
- Temporary Gas System Control, Monitoring and Safety Interlocks
Back-up and Test Hardware:
- vROM (4 available?)
- Calorimeter Optical Transceiver Module (#?)
|
- Dataflow/OEP (preferably w/ Calibration framework)
- Detector control/ EPICS
- Run Control
Back-up Software:
- vROM Stand-alone Driver
- Dataflow-ProtoII Hybrid DAQ System
|
Electronics Install and Test,
Full System |
6/1-7/16 |
- HV System + cables
- LV System + cables
- 48 FEAs w/cabes
- 4 DIOM
- 8 TIOM
- 2 ROM + 1 FCDM/FCPM/9u crate
- Fiber-optic cables
- Forward endplate env. monitoring modules
- Slow Controls 6-u crate w/
-
- CANBUS interface
- CAENET interface
- SIAMs
- VSAM
- Cosmic trigger counter
- Workstation
- Full Gas System Electronics
|
- Dataflow/OEP (w/ Calibration framework)
- Detector control/ EPICS
- Run Control
|
| Cosmic Run 0 |
7/17-8/13 |
full complement of electronics and software as listed above.
- + Electronics for BABAR DC Trigger tests (?)
|
(as above)
|
Cosmic Run 1,2,3
in BABAR |
9/18-1/15/99 |
(as above)
|
(as above)
|