| Monday |
Tuesday |
Wednesday |
Thursday |
Friday |
Saturday |
Sunday |
| 2 |
3 |
4 |
5 |
6 |
7 |
8 |
| |
|
DCH arrives at SLAC |
DCH uncrated; helium flow established |
Helium flush |
Tension test performed on 1200 wires |
|
| 9 |
10 |
11 |
12 |
13 |
14 |
15 |
| Gas and safety system assembly |
Gas and safety system assembly |
Gas and safety system assembly |
Gas system assembly and review |
Gas and safety system assembly |
|
|
| 16 |
17 |
18 |
19 |
20 |
21 |
22 |
| Gas and safety system assembly |
Gas and safety system assembly |
Gas safety system assembly |
Gas system assembly and review |
Safety approval to run LAB gas system;
helium:isobutane flush |
Helium:isobutane flush |
HV test |
| 23 |
24 |
25:
Bloom |
26:
Wilson |
27: Wilson |
28: Wilson |
29: Wilson |
| Safety trip; helium:isobutane flush |
Safety trip; helium:isobutane flush |
Helium:isobutane flush; HV test |
Start individual wire scan |
Wire scan continued and Xenon
injection; Assemble and test cradle |
Wire scan started but no activity
detected; helium flush |
Helium flush |
30: Bloom |
31: Bloom |
|
|
|
|
|
| Test cradle and modify |
Retest cradle; extract DCH from mobile frame |
|
|
|
|
|