BaBar Computing Level 3 Milestones (Baseline) =============================================== B8143 960510 Online Testbench Deployment Online dataflow prototype based on EPICS and VxWorks available for testbench use by detector subsystems (DCH, SVT, EMC probably first). B8227 961101 Data Storage Design Review Conclusion of evaluation studies and review prior to implementation of prototype data storage system. B8149 970401 HER Online System Deployment Low-rate data acquisition system based on EPICS and VxWorks for HER commissioning studies. B8645 970401 Mock Data Challenge 1 Demonstrate complete reconstruction chain, produce and process "signal" and "background" events (~50k), for mock data analyses. No performance benchmarks, alignment or calibration information B8057 970630 Switch Architecture Decision Technology and architecture decision on event builder switch, for procurement. B81512 971201 BaBar On-line Ready for Initial Electronics Commissioning Baseline version of on-line software and hardware ready for commissioning tests in experimental hall. B8780 971201 Production Fast Simulation Deployment Complete fast simulation Monte Carlo program available for production. B8008 980430 Production Farm Hardware Decision Final procurement decision for online/level 3 compute farm acquisition. B8152 980501 BaBar On-line ready for Detector Commissioning On-line software and hardware ready for production use in a multi-partition environment for parallel detector commissioning. B8660 980601 Mock Data Challenge 2 Mock data challenge 2, as for mock data challenge 1, plus ~500K events allowing up to 10 complete analyses. Basic resolving of alignment and calibration constants. Reconstruction run on Online Farm with data to permanent storage. Benchmarking against requirements for 10**8 events. B8837 980930 Production OO Simulation Deployment Full GEANT4-based simulation suitable for production Monte Carlo dataset generation.